반도체 프로브 공정에서의 2단계 계층적 생산 계획 방법 연구
* 본 문서는 배포용으로 복사 및 편집이 불가합니다.
서지정보
ㆍ발행기관 : 한국산업경영시스템학회
ㆍ수록지정보 : 산업경영시스템학회지 / 38권 / 4호
ㆍ저자명 : June-Young Bang
ㆍ저자명 : June-Young Bang
목차
1. Introduction2. Problem Statement
2.1 MIP Model for Lot Transfer Problem
2.2 Discrete Event Simulation for Detailed Scheduling
3. Lagrangian Relaxation Approach forHigher Level Decision
4. Computational Experiments
5. Conclusion
영어 초록
We consider a wafer lot transfer/release planning problem from semiconductor wafer fabrication facilities to probing facilities with the objective of minimizing the deviation of workload and total tardiness of customers’ orders. Due to the complexity of the considered problem, we propose a two-level hierarchical production planning method for the lot transfer problem between two parallel facilities to obtain an executable production plan and schedule. In the higher level, the solution for the reduced mathematical model with Lagrangian relaxation method can be regarded as a coarse good lot transfer/release plan with daily time bucket, and discrete-event simulation is performed to obtain detailed lot processing schedules at the machines with a priority- rule-based scheduling method and the lot transfer/release plan is evaluated in the lower level. To evaluate the performance of the suggested planning method, we provide computational tests on the problems obtained from a set of real data and additional test scenarios in which the several levels of variations are added in the customers’ demands. Results of computational tests showed that the proposed lot transfer/planning architecture generates executable plans within acceptable computational time in the real factories and the total tardiness of orders can be reduced more effectively by using more sophisticated lot transfer methods, such as considering the due date and ready times of lots associated the same order with the mathematical formulation. The proposed method may be implemented for the problem of job assignment in back-end process such as the assignment of chips to be tested from assembly facilities to final test facilities. Also, the proposed method can be improved by considering the sequence dependent setup in the probing facilities.참고 자료
없음"산업경영시스템학회지"의 다른 논문
- 고령자를 위한 무동력 기립보조의자 개발7페이지
- 국내 무인항공기의 경로계획 연구14페이지
- 물류자동화 시스템의 효율적 구축을 위한 컨설팅 방법론 제안 : K기업의 사례를 중심으로10페이지
- 기업 정보보안 전략 수립을 위한 보안 사고 유형 분류에 관한 연구9페이지
- 시니어전용 기능성 깔창의 체계적인 개발 및 효과분석9페이지
- 점진성형에서 형상 정밀도에 영향을 미치는 공정 변수7페이지
- 제품-서비스 시스템 개발을 위한 객체 지향 설계 프레임워크 개발9페이지
- 이산사건 시뮬레이션 시스템을 활용한 생산성 개선 사례 연구10페이지
- 열화되는 성능 파라메터를 가지는 시스템의 신뢰성 예측에 관한 연구7페이지
- 최소 종료시간 사격 스케줄을 위한 분지계획법 알고리즘 연구10페이지